There's a time to compress the schedule, and a time to leave breathing room. I've compressed this week, for a number of reasons. I've been lucky enough to build some good relationships with key trades that can sometimes delay things for some time - today, CoXCo, the City subcontractor, was nice enough to jump a huge queue in order to do my sewer/water upgrade on site.
Doing this meant I was potentially pissing off the waterproofing guy, and subsequently everyone else (even the crane guy to remove the forms...which should have been done yesterday). To make a long story short, the day worked out ok, though now I've put even more pressure on the schedule for the rest of the week. Fingers crossed!